The account given herewith derives from the 9 year long monitoring Program of a plant originally intended to dispose of rain-water to 3 seepage wells. Sequences of water column and bottom temperature values have been collected every 5 minutes by the 3 data loggers. Inside the building overlooking a seepage well, two recording fissure-metres have been taking hourly readings. The thermo-hydraulic data-base now consists of 3×10^6 records. Data sequences have been filtered and processed by suitably designed algorithms. Plant response to rainstorms has been quantified, the well thermo-hydraulics has been modeled. Water seepage has been shown to cause building deformation. Evidence came from an accident: a water circulation plant ran out of control and sent 800 cubic metres of water to a well in 47 days. The fissure meter inside the building above the well showed a delayed response by the structure. The monitoring scheme is portable to other Programmes which manage water resources
Crosta, G. (2027). The hydro-geophysical monitoring of a water disposal plant interacting with foundation soil. In The 21st IWA Leading Edge Conference on Water and Wastewater Technologies online preprint. London.
The hydro-geophysical monitoring of a water disposal plant interacting with foundation soil
Crosta, Giovanni Franco
Primo
2027
Abstract
The account given herewith derives from the 9 year long monitoring Program of a plant originally intended to dispose of rain-water to 3 seepage wells. Sequences of water column and bottom temperature values have been collected every 5 minutes by the 3 data loggers. Inside the building overlooking a seepage well, two recording fissure-metres have been taking hourly readings. The thermo-hydraulic data-base now consists of 3×10^6 records. Data sequences have been filtered and processed by suitably designed algorithms. Plant response to rainstorms has been quantified, the well thermo-hydraulics has been modeled. Water seepage has been shown to cause building deformation. Evidence came from an accident: a water circulation plant ran out of control and sent 800 cubic metres of water to a well in 47 days. The fissure meter inside the building above the well showed a delayed response by the structure. The monitoring scheme is portable to other Programmes which manage water resources| File | Dimensione | Formato | |
|---|---|---|---|
|
LET2027_Characterisation.pdf
Solo gestori archivio
Descrizione: Documento basato su modello in docx predisposto dall'Organizzazione del congresso; documento scritto con Pages version 12.0 (7033.0.134) su macchina Apple MacBook Air M2 (2022) con sistema operativo MacOs Monterey v. 12.5 (21G72), convertito in PDF con macOS Version 12.5 (Build 21G72) Quartz PDFContext il 2026-1019 13:45 UTC+2
Tipologia di allegato:
Submitted Version (Pre-print)
Licenza:
Tutti i diritti riservati
Dimensione
1.89 MB
Formato
Adobe PDF
|
1.89 MB | Adobe PDF | Visualizza/Apri Richiedi una copia |
I documenti in IRIS sono protetti da copyright e tutti i diritti sono riservati, salvo diversa indicazione.